Skip to content

Why Cabo Verde paired new wind turbines with batteries

The Cabeólica expansion on Santiago adds generating capacity, while batteries support power systems on several islands.

By AfricaNewsWatch Editorial Desk · Published · Event date

The Noor III solar tower near Ouarzazate, Morocco, in 2018.
Contextual image. The Noor III solar tower near Ouarzazate, Morocco, in 2018. Marc Lacoste · Photo credits

In December 2025 Cabo Verde inaugurated new wind turbines and a battery system under the Cabeólica expansion. An October 2026 investor presentation from the African Development Bank put the project back in focus as an example of how an island power system can handle more renewable generation. The expansion builds on four wind farms on Sal, São Vicente, Boa Vista and Santiago.

The European Investment Bank described 13.5 megawatts of new wind capacity on Santiago and 26 megawatt-hours of battery storage spanning four islands. Those units track different things. The turbines add a way to generate electricity when the wind blows. A battery can store energy already generated and help the local system respond as demand or output changes.

The EIB reported that the additional financing exceeded €39 million and identified the African Development Bank as a co-financier. Its announcement put the expected share of electricity from the expanded wind project at 30 percent, up from about 20 percent reported at the time. That was a projection, and actual generation shares can vary with weather, demand, operation and the period measured.

Sources and further reading

Share by email